Monday, September 26, 2011

Rained Out Through the Weekend

We were not able to work this weekend due to heavy rain. It rained all day Friday, Saturday, and Sunday, which meant that it was too wet to work on the foundation Monday.
















- Posted using BlogPress from my iPad

Monday, September 19, 2011

First Footings Poured

We started pouring the footings this afternoon. We were able to place the steel in the entire left side of the exterior footings and inspect it. We then subsequently poured this side.

The footings were inspected by the city, the steel was inspected by the architect and the site testing company, and the footing bearing capacity was tested by the site testing agency.

















- Posted using BlogPress from my iPad

Friday, September 16, 2011

Footings Started

We started digging footings today. The crew arrived this morning and batter boards were quickly erected and the digging started. We started in the rear near the baptismal font and worked towards the front. We will have to pour the footings in several different pours, since the footings are at different depths and because of possible rain next week.












Thursday, September 15, 2011

Form Boards On Site, Concrete To Start Soon

Now that the soil has dried out a little, we have passed our soil compaction tests and can proceed with concrete. The forms were delivered yesterday and the equipment and workers will arrive tomorrow to start work.



The site contractor finished the ponds and installed the stone around the drain outlets.



The area where the pavilion is to be made has had the poor soils beneath it cut out and relocated. It is ready for engineered fill to be brought in an placed in lifts up to grade.


- Posted using BlogPress from my iPad

Monday, September 12, 2011

Pad waiting to dry out

After having removed the surcharge, we kept rolling the pad. We were not able to achieve compaction though, due to too much moisture being present in the soil.

As soon as we can get the moisture out of the pad we can continue with the foundation.

The video below shows that the pad is pumping under the weight of the roller.








Building corners were also set by the surveyors.



- Posted using BlogPress from my iPad

Thursday, September 8, 2011

Started Stripping Surcharge Material

Today we were able to start stripping the surcharge material from the building pad again following Tuesday's rain. The material was still wet, but we were able to remove about half of it and clear the pad for the concrete crew coming Monday.

We were not able to compact the material since it was still too wet, but hopefully will be able to do so tomorrow as the material dries out.












- Posted using BlogPress from my iPad

Grease Trap installed

The grease trap was delivered and installed today allowing the site contractor to finish laying the rest of the sewer pipe through the building.






- Posted using BlogPress from my iPad



Wednesday, September 7, 2011

Tuesday, September 6, 2011

And Let There Be Light!


The power was finally connected to the trailer. Just in time for the cooler temperatures to come in and not need the A/C, thanks Hurricane Irene for delaying the power company.

Now, more can be accomplished since my laptop battery will not die at 10:00 am with a way to charge it.

Surcharge Stripping Delayed by heavy rains



We were scheduled to strip the 2' of surcharge material from the building pad today, but could not due to heavy rains. After waiting a month, we are now able to remove the extra material placed on the building pad designed to speed up any settling under the building that may take place.

We received almost an inch of rain just as we started working. The long down pour will unfortunately delay the work for a couple of days, since the muddy conditions will not allow dump trucks on site to haul the material to other areas on site.