The curb crew started forming the curb. Due to rain, no pour was made. They will continue to form curb and pour tomorrow if it is not too wet and muddy tomorrow.
The mammoth 16" water line was tapped and back flow preventers set. The site utility contractor is now running the fire and domestic water lines to the building.
Tapping sleeve being installed.
Back flow preventers installed and 8" fire line and 2" copper water line laid out for install. Both are more than 48" deep.
The anchor bolts for the hold downs are mostly installed. They were drilled 14" deep, sucked out with a vacuum, blown out with air and then epoxied and set.
Hole drilled and cleaned out.
18" threaded rod ordered from local supplier pre cut.
The framer started decking the roof today. I spent a lot of time on the roof checking the nailing pattern, making sure they fixed any areas I asked them to correct.
My marks showing missed, under driven, or over driven nails.
A couple of under driven nails that were later fully nailed by hand.
A corner that stuck up a little before it was fixed.
Some minor mistakes were made in the floor slab depression and these items have been fixed.
The non load bearing wall surrounding the basketball floor depression was removed while forms were installed and poured with high strength non shrink grout. The walls were then replaced after the grout was cured.