A majority of the curb has been poured. We are currently pouring the last island and the other side of the street entrance. We only have to pour a straight section in front of the pavilion and at the curb drains.
Monday, December 19, 2011
Concrete curb is almost done
A majority of the curb has been poured. We are currently pouring the last island and the other side of the street entrance. We only have to pour a straight section in front of the pavilion and at the curb drains.
Friday, December 9, 2011
Roughing in all trades
Now that the temporary roof is on, all the trades are working to finish the interior walls to get things up to the attic space.

Most of the plumbing is roughed into the bathrooms and serving areas.

Drywall is hung in the inspected and insulated attic space. Sprinkler pipe and ductwork is starting to be suspended from the ceiling in the mezzanine.


Ductwork is being hung starting in e lower areas all working back up to the mezzanine.


Curb is poured around most of the parking areas.
Most of the plumbing is roughed into the bathrooms and serving areas.
Drywall is hung in the inspected and insulated attic space. Sprinkler pipe and ductwork is starting to be suspended from the ceiling in the mezzanine.
Ductwork is being hung starting in e lower areas all working back up to the mezzanine.
Curb is poured around most of the parking areas.
Monday, November 28, 2011
Fire suppression, electrician, hvac all working
Curb crew starts
Friday, November 18, 2011
Water tap made and back flow preventers set
The mammoth 16" water line was tapped and back flow preventers set. The site utility contractor is now running the fire and domestic water lines to the building.

Tapping sleeve being installed.

Back flow preventers installed and 8" fire line and 2" copper water line laid out for install. Both are more than 48" deep.

The correct 2" type k copper pipe being used

Tapping sleeve being installed.
Back flow preventers installed and 8" fire line and 2" copper water line laid out for install. Both are more than 48" deep.
The correct 2" type k copper pipe being used
Exterior sheathing almost complete
Monday, November 14, 2011
Windows arrive on site
Anchor bolts drilled and epoxied
Remaining trusses set
Roof decking installed
The framer started decking the roof today. I spent a lot of time on the roof checking the nailing pattern, making sure they fixed any areas I asked them to correct.


My marks showing missed, under driven, or over driven nails.


A couple of under driven nails that were later fully nailed by hand.


A corner that stuck up a little before it was fixed.


My marks showing missed, under driven, or over driven nails.
A couple of under driven nails that were later fully nailed by hand.
A corner that stuck up a little before it was fixed.
Friday, November 11, 2011
Steel columns and beams set
Subscribe to:
Comments (Atom)