A majority of the curb has been poured. We are currently pouring the last island and the other side of the street entrance. We only have to pour a straight section in front of the pavilion and at the curb drains.
Monday, December 19, 2011
Concrete curb is almost done
A majority of the curb has been poured. We are currently pouring the last island and the other side of the street entrance. We only have to pour a straight section in front of the pavilion and at the curb drains.
Friday, December 9, 2011
Roughing in all trades
Now that the temporary roof is on, all the trades are working to finish the interior walls to get things up to the attic space.

Most of the plumbing is roughed into the bathrooms and serving areas.

Drywall is hung in the inspected and insulated attic space. Sprinkler pipe and ductwork is starting to be suspended from the ceiling in the mezzanine.


Ductwork is being hung starting in e lower areas all working back up to the mezzanine.


Curb is poured around most of the parking areas.
Most of the plumbing is roughed into the bathrooms and serving areas.
Drywall is hung in the inspected and insulated attic space. Sprinkler pipe and ductwork is starting to be suspended from the ceiling in the mezzanine.
Ductwork is being hung starting in e lower areas all working back up to the mezzanine.
Curb is poured around most of the parking areas.